NEW DELHI: The Union Cabinet sanctions a proposal by the Ministry of Power for higher allocation of electricity to Telangana and Jharkhand from the under-construction projects of National Thermal Power Corporation Limited (NTPC) on February 6.
85 per cent power will be allocated to Telangana which will be generated from Telangana Super Thermal Power Project (TSTPP) with 4000 MW of NTPC and 85 per cent power will be allocated to Jharkhand from the expansion project of Patratu Thermal Power Station (PTPS) with 4000 MW of Patratu Vidyut Utpadan Nigam Limited (PVUNL). PVUNL is a subsidiary company of NTPC.
Projects will be established in two phases. Phase-I of both
the projects are under construction. TSTPP will comprise two units of 800 MW
each and second phase for three units of 800 MW each and PTPS will comprise
three units of 800 MW each in the first phase and two units 800 MW each in the
second phase.
TSTPP will be set up at Ramagundam in Peddapalli
district while the PSTP station of Jharkhand will come at Patratu in Ramgarh
district.
Higher allocation of power to Telangana from TSTPP will ensure that the Central
government has taken the necessary measures as enumerated in the 13th
Schedule of the Andhra Pradesh Reorganisation Act, as per an official
release.
Representative Image NEW DELHI: The India Meteorological Department (IMD) has issued a warning regarding an…
Representative Image JAMMU and KASHMIR: The National Green Tribunal (NGT) has called upon the Central…
Representative Image NEW DELHI: The 19th edition of the United Nations Forum on Forests (UNFF…
Representative Image MUMBAI, Maharashtra: The Brihanmumbai Municipal Corporation (BMC) has published a list of 188…
Representative Image CHENNAI, Tamil Nadu: The Greater Chennai Municipal Corporation is mulling the plan to…
Representative Image TRICHIRAPALLI, Tamil Nadu: Faulty Streetlights on the newly built Kollidam Bridge in Trichy…